The Construct Hybrid Operating Room project is the build out of an existing shell space in the surgery suite at the Kansas City, Mo VAMC. It encompasses approximately 1,930 sf. The build out consist of a 1,200 sf hybrid operating room, control room, equipment room, scrub station and sterile storage.

Hybrid Operating Room
// Healthcare
Solving Technically Complex Problems
The largest challenge of this project is maintaining operation of the existing surgical suite. Guidon Design is currently finalizing the construction documents for this complex phased project.
The overall intent of the project is to modernize the services at the VA allowing doctors to work with the latest equipment and veterans to receive the best treatment and care. Approximate Construction Cost: $2.5M
Client
The Department of Veterans Affairs Kansas City VA Medical Center
Location
Kansas City, MO
Size
1,930 sf
Market
Healthcare
Services
Architecture Interior Design Structural Engineering